The Challenge

To develop an office complex adjacent to the M60 motorway.

Key Considerations

The scheme that was submitted for planning included seven blocks with one section of the development including blocks A-C and the other D-G. The client however wanted to build these out separately, therefore, due to access and the logistics of the building, it was agreed that the additional phase should be constructed on an occupied site: blocks D-G.

The Outcome

The design was in development for these four blocks when unfortunately Covid impacted. At this point, the client decided to construct the larger block only (block G), but continue with design development and the production of the bills, of quantities for D-F, at the same time. The project is about to go out to tender and we will then have three newly refurbished blocks ready to tender.

Our Services

  • Project Management, including Contract Administrator
  • Quantity Surveyors.

 